Brett Earnest

General Manager, Mission Critical and Advanced Manufacturing Suffolk Construction Company

Seminars

Wednesday 2nd December 2026
Case Study: Getting Campus Planning Right to Avoid Infrastructure-Driven Scope Creep at Scale
10:50 am
  • Testing campus layouts against real-world constraints by validating permitting, power, utilities, easements and access requirements before designs are finalized
  • Mapping utility, transmission and MV distribution pathways early to prevent rework across roads, parcels and stakeholders
  • Aligning substation and generation strategies with constrained grid capacity and longer interconnection timelines
  • Establishing cross-disciplinary communication models early to create governance around interfaces rather than disciplines
  • Treating Early Works as a risk mitigation strategy by using enabling works to remove schedule uncertainty, rather than simply preparing the site
Brett Earnest